New Well Status

October 12, 2009

 

Ron Stafford, member

BMDWCA Board of Directors

 

1.  The piping and new pump and motor have been installed on the new well;

2.  Valving has been completed to allow us to operate the old and new wells independently.  The old well is Well #1 and the new well is Well #1A;

3.  New electrical configuration has been incorporated into the well house to allow us independent operation of each well;

4.  New plumbing for both wells #1 and #3 should be completed by the end of October;

5.  We hope to run the new well into the stream east of the pond for about a week soon;

6.  The Rio Grande Sun advertisements have been completed and if no comments are received from the public we anticipate a letter from the State Engineer allowing us to begin operations of the new well;

7.  We are trying to get the pressure switch calibrated on the new well by HGS or BioWest soon.