Thanks in large part to
the efforts of Board of Directors member Ron Stafford, we are on the verge
of getting a new well.
Background information is given in Ron’s March 2009 progress report. Drilling for the new well was
started during the week of June 22, 2009, and drilling was completed on
July 15, 2009 at a depth of 600 feet.
Pictures taken by Levi Sandoval, our Certified Water Operator, of
the drilling process can be found here. Ron’s status report as of July 16,
2009 can be found here and his status
report as of October 12, 2009 can be found here.
|
|